Johny,
1. There is a typo here.
The task "Create P1364-D5" should end on Jan 13, 2005, not Jan 3.
It has the same dates as P1800-D3.
An additional warning is that the PLI 1.0 deprecation proposal
also involves reformatting work.
Nevertheless, I still believe as of now, that the Jan 13 date
is achievable with a high degree of confidence.
2. Regarding "Optional P1364 meeting to review D4 comments":
A Jan 3 date is listed.
In fact, Tom and Karen have reserved slots for meeting on the following
Monday, Jan 10, not Jan 3.
As of now, however, the only comment that was received is a single
trivial typo.
3. One last point: I don't expect a problem with WG approval of the
ballot draft at the Feb 17 meeting. However, in the unlikely event
that there is a problem, that does not allow the editor any time
to fix anything before Feb 18. However, as a goal, it is fine.
On Tue, 14 Dec 2004, Srouji, Johny wrote:
> Hi All,
>
>
>
> Attached is the modified version of P1800 schedule including 1364
> milestones as incorporated under one sheet.
>
> We shall go over this tomorrow in our WG F2F meeting.
-- Shalom Bresticker Shalom.Bresticker @freescale.com Design & Verification Methodology Tel: +972 9 9522268 Freescale Semiconductor Israel, Ltd. Fax: +972 9 9522890 POB 2208, Herzlia 46120, ISRAEL Cell: +972 50 5441478 [ ]Freescale Internal Use Only [ ]Freescale Confidential ProprietaryReceived on Tue Dec 14 23:32:18 2004
This archive was generated by hypermail 2.1.8 : Tue Dec 14 2004 - 23:32:19 PST